June 22, 2026 - Silver Springs - A new 345 kiloVolt (kV) transmission segment would be added to the Greenlink West Transmission Project so Microsoft can power a data center at Silver Springs. There was no public comment but it can be appealed.
"In order to construct and operate the transmission line across BLM-administered public land, the Project would require a right-of-way (ROW) grant from the BLM. Because the ROW grant would be owned and operated by NV Energy, the grant is being sought in its name; however, Microsoft Corporation (Microsoft) is the entity coordinating environmental permitting efforts on NV Energy’s behalf under an existing High Voltage Distribution Agreement between Microsoft and NV Energy as the anticipated first of multiple users of the proposed Project. To initiate the grant process, NV Energy submitted to the BLM a Standard Form 299 Application for Utility and Transportation Systems on Federal Lands and a Project Plan of Development (POD) in September 2024. A revised POD was submitted to BLM in April 2026 (Stantec 2026). "
The Proposed Action includes the construction and operation of a new 345-kV transmission line fold (two lines total comprised of a northern and southern segment) to connect to the Greenlink Transmission Project. The northern segment of the transmission alignment would be approximately 5.7 miles long and the southern segment would be approximately 5.1 miles long for a total of 10.8 miles of transmission line. The total proposed disturbance under the Proposed Action would include up to 540.6 acres.
May 15, 2026 - Reno, NV - The old saying goes: "All roads lead to Rome." In the modern state of affairs in Nevada, it seems that all roads lead to data centers. Greenlink West Transmission Project, currently approved and under construction, is mostly connecting up to new data centers and other industrial facilities at the Tahoe-Reno Industrial Center east of Reno in northern Nevada. More data centers are planned near Silver Springs, NV.
Data centers here will require enormous amounts of energy, planned to come from natural gas power plants at Apex, north of Las Vegas, massive planned solar projects in Nevada's western deserts along the route, as well as existing natural gas power east of Sparks. The huge substations being built now in Amargosa Valley and Big Smoky Valley in Esmeralda County for Greenlink give an indication of the megawatts of solar projects that can be fed into the line.
A map of planned data centers around Silver Springs, Nevada, fed by the Greenlink West Transmission Project. Sheet obtained in Stagecoach, NV, via social media.
Yet NV Energy, the Investor-Owned Utility building Greenlink, has simultaneosuly announced that it will be cutting off power to the community of Lake Tahoe because of the need to direct more power to data centers in northern Nevada, concentrated around the Tahoe-Reno Industrial Center. 5,900 megawatts may be needed by 2033 for data centers. Lake Tahoe in adjacent California has 49,000 residents which receive power from Liberty Utilities, which sources 75% of electricity from NV Energy. The local utility has until May 2027 until NV Energy ends its power supply agreement with Lake Tahoe.
Lake Tahoe depends entirely on NV Energy transmission infrastructure, and is not within the California Independent System Operator area. Building it's own transmission line west across the high Sierra would costs "hundreds of millions" of dollars according to an interview with Liberty in Fortune.
There may not be enough land to build solar projects to replace this energy. Liberty might be looking to buy energy from out of state and continue to use NV Energy transmission lines.
Data centers already use 22% of Nevada's electricity in 2024, and that number is rising.
Meanwhile we watch Greenlink West Transmission Project relentlessly move forward in construction, bulldozing new roads into desert ecosystems, carving tower pads into mountain sides, filling water trucks with locally-pumped groundwater, and opening up large swaths of the western Nevada wild outback to solar energy development.
For massive data centers.
The new Sagebrush Substation in Amargosa Valley, NV, under construction now. The 100-plus acre substation connects with Greenlink West and will serve as a collector hub for large-scale solar projects on the east side of Death Valley National Park.
Greenlink West Transmission Project steel H-pole under construction, almost 180 feet tall, north of Las Vegas, NV.